Wadi Safar – Diriyah Gate Development Authority (DGDA)

Scope of Work

Works will be undertaken in two Phases:

  • Phase 1 – Construction of Nursery
  • Phase 2 – Operation & Maintenance of Nursery / Tree Management for 2 Years

The Nursery Construction is comprised of the following main components:

  1. Nursery Site Construction
    • Site Grading 70,000 m2
    • Parking and roads 5,000 m2
    • Site Lighting 25 Nos
    • Fencing & Gate 1,200 m
    • Irrigation network & Utilities      60,000 m2

 

  1. Construction of Nursery Management Buildings
    • Office Building + Messing Facilities 300 m2
    • Storage Facility 100 m2
    • Soil Mixing Shed + Washdown area 200 m2
    • Open in-ground area 60,000m2

The Operation & Maintenance / Tree Management is comprised of the following services:

  1. Operation & Maintenance / Tree Management
    • Survey, Health Checking & Tagging of Trees >50,000 Nos
    • Disposal of diseased trees
    • Treatment for palm trees against red weevils
    • Palm/Shade Trees Transplanting in Nursery >10,000 Nos
    • Watering, Pruning & Maintenance of Trees >24 Months